What's next?

The framing for the rooms are complete. It is expected that the HVAC system will be installed next week. Once the HVAC system is installed the electricians can begin work. The plumber is expected to begin the next portion of the job this week. It is really starting to take shape now!

New Location Update

The building permit was approved yesterday, now construction can begin! The concrete is being poured on Friday! Things should move along quickly now. Here are some pictures after the plumbing has been roughed in.

Reminder...

There is not karate classes this week, Monday, March 28th and Wednesday, March 30th. Our final session at the Maryland Heights Community Center begins on Monday, April 4th and Wednesday, April 7th. We expect to be in the new location after this final session. Enjoy the break this week and we look forward to seeing you next week.